CD-S1000
13
Fig. 5
When checking the AUDIO P.C.B.:
• Put the rubber sheet and cloth over this unit. Then
place the P.C.B.s upside down on the cloth and
check it. (Fig. 6)
• Reconnect all cables (connectors) that have been
disconnected.
Use to use the extension cable before connection the
following connectors.
AUDIO P.C.B. CB2–DIGITAL P.C.B. CB303
12P, 450mm P=1.25 (MF112450)
• When connecting the flexible flat cable, be careful
with polarity.
• In this unit, the ground of P.C.B.s shown below is
connected to the rear panel and chassis. When these
P.C.B.s are removed from the rear panel, connect the
ground point to the rear panel or chassis, using a
ground lead wire or the like. (Fig. 6)
C
D
E
F
G
H I
I
H
I
6. Removal of Loader Unit
a. Remove 4 screws (C) and then remove the support
audio. (Fig. 4)
b. Remove CB301-302, CB612 and CB903. (Fig. 4)
c. Remove 4 screws (D). (Fig. 4)
d. Remove 2 push rivets and then remove support F on
both sides of the loader unit. (Fig. 4)
e. Remove 2 screws (E) and then the frame mecha L.
(Fig. 4)
f. Remove 2 screws (F) and then remove the frame
mecha R. (Fig. 4)
g. Remove 2 screws (G) and then remove the loader
unit. (Fig. 4)
● When installing the Loader Unit:
When installing the loader unit, adjust the clearance be-
tween the front panel and lid so that it becomes equal at
the top, bottom, right and left.
1. Loosen 2 screws (H) and 2 screws (I). (Fig. 7)
2. Position the support F on both sides with its flat
portion facing upward. (Fig. 7)
3. Viewing from the front, confirm the lid position. (Fig. 7)
4. Tighten the screws on the side with higher lid inclina-
tion (screws (I) in the case shown below). (Fig. 7)
5. Turn the support F on the side with lower lid inclina-
tion clockwise gradually until the lid is positioned
horizontally. (Fig. 7)
6. With the lid adjusted at the horizontal position,
tighten other screws (screws (H) in the case
shown below). (Fig. 7) To change the position up-
ward at this time, loosen screws (I) and then turn
the support F clockwise gradually.
* Be sure to make adjustment from either side only.
7. Repeat opening and closing the tray some times
and confirm to make sure that the same clearance
between the front panel and lid is obtained at the
top, bottom, right and left.
Fig. 6
Fig. 7
Lid
Support F
Flat portion
H
H
I
Support F
Flat portion
I
B
AUDIO P.C.B.
DIGITAL P.C.B.
CB303
CB2
Rubber sheet and cloth
Ground lead
ST1
FG
Ground lead
MF112450