088U7040 / VIIKD12P
© Danfoss | FHH | 2016.07 | 1
Installation overview
Installation
The FHM-CN2 must be connected to a system
according to the illustrations.
A
E
B
C
1 4
6
2
5
3
E1
Fig 2.
A
Primary water side (horizontal direction)
B
Secondary water supply
C
Secondary return
D
Primary water supply (vertical direction)
E
Primary return
1. Remove the union nuts 1, 2 and 3 and gasket
5 from mixing shunt which to be used in steps
below, as shown in Fig. 2.
2. Pre-mounted union nut 1 for connection to
the primary side supply pipe . The union nut
1 to control valve 4 must be tightened with a
torque of at least 85 Nm without any sealing
materials, as shown in Fig. 2.
3. Pre-mounted union nuts 2 and 3 for connec-
tion to the secondary side pipe or directly on
a Danfoss manifold. The union nuts 2 and 3 to
mixing shunt must be tightened with a torque
of 30 to 40 Nm with enclosed flat gasket, as
shown in Fig. 2.
4. The end of primary side return pipe E1 for con-
nection to primary side return pipe E.
5. Remove the blue cap 6, as shown in Fig. 2.
6. FTC thermostatic sensor is in package. Mount it
on the valve according to the enclosed instruc-
tion, as shown in Fig. 3.
FTC
Fig 3.
Fig. 1: Overview
Installation Guide
FHM-CN2
Pre-assembled Mixing Shunt