Installation Guide FHM-CN5 Pre-assembled 3-Way Mixing Shunt
2 | © Danfoss | HydronicS | Sub-systems | 2023.07 AN45665685584401-CN0101
Tips
RoHS compliance
1. If the primary side pipe is coming from the side,
the bend 1 must be tightened with T-connec-
tion 4 with a torque of 30 to 40 Nm.
2. Connection 5 are tightened from the factory.
Please double check the connection 5 during
installation. Please tighten at a torque of 15 to
25 Nm if loosening or leaks occur due to trans-
portation or moving.
Supply of primary side
Supply of secondary side
Return of secondary side
Return of primary side
B
C
A
D
A
C
B
D
1
4
5
5
Part Name Hazardous Substances Table
Pb Hg Cd Cr(VI) PBB PBDE
Pump X O O O O O
Brass parts X O O O O O
O: Indicates that this hazardous substance contained in all of the homogeneous material for this
part is below the limit requirement in GB/T 26572.
X: Indicates that this hazardous substance contained in at least one of the homogeneous material
for this part is above the limit requirement in GB/T 26572.